Machining time: calculation from feed rate
Estimate the cutting time per pass and the total for several identical passes. The calculation uses the distance traveled by the tool and its constant linear feed speed.
Machining time at constant feed
Distance travelled at the entered feed during one pass; approach and exit are included only if counted.
Constant feed actually achieved over the entire travel, strictly positive.
Integer number of passes with the same length and feed, at least 1.
Initial values are examples.
Results
Substitution in SI units
The total repeats the same travel at constant feed; return moves, acceleration, tool changes and auxiliary times are not added automatically.
Travel in one pass
Estimated reading time : 4 min · 677 words
Calculation details
The steps below use the inputs and units selected in the calculator. ; inverses and . T is the combined time of N identical passes, never a single-pass time. L includes cutting and any approach and runout at the same feed: L = La + Lc + Ld. Segments at another speed, rapid returns, setup, loading and tool changes must be timed separately. Inverse feed is a kinematic requirement; cutting feasibility and machine limits still need checking.
02 · Total cutting time
Cutting time and number of passes
Theoretical cutting time is the time needed to travel a length at constant feed speed. The total multiplies this time by the number of identical passes. The distance may include a known overtravel if you explicitly include it.
Formulas and symbols
Choose time, feed or travel per pass. The inverses use the total time of N identical passes. Displayed inputs follow the selected unknown; equals .
- L: cutting distance per pass, default displayed unit: mm.
- vᶠ: linear feed speed, default displayed unit: .
- N: number of identical passes, dimensionless.
- t: cutting time per pass, default displayed unit: s.
- ttotal: total cutting time, default displayed unit: s.
Guidance for interpreting results
| Quantity or condition | Interpretation |
|---|---|
| Cutting time | Length divided by linear feed speed |
| Complete machine time | Add known non-cutting times |
| Different passes | Calculate each length and feed speed separately |
| Feed in | |
| Time in seconds | t [s] = [mm]/vᶠ [] |
Sandvik Coromant — Turning Formulas and Definitions ; KEYENCE — Face Milling Formulas.
Worked examples
Example 1: 100 mm at , three passes
One pass takes 30 s; the three passes total 90 s.
Example 2: 250 mm at
One pass takes 30 s.
Example 3: Two one-metre passes
This exercise checks the conversion from minutes to seconds. Both passes are identical and feed is constant; return and preparation times are excluded.
, : ; two passes take 120 s.
Example 4: Facing 600 mm in 4 passes at
One 600 mm pass at takes 90 s. Four identical passes total 360 s, or 6 minutes of cutting time, excluding rapid traverses and changeover times.
; .
Assumptions and limitations
Constant feed and identical passes. Rapid returns, acceleration, tool changes, approaches not included in the distance, workpiece loading and setup time are not calculated.
Common mistakes
Entering feed per revolution instead of linear speed; entering 200 in to represent ; multiplying by the number of passes twice; presenting this cutting time as the complete machine time.
Frequently asked questions
Can I enter feed per revolution?
No. The field expects a linear speed. Convert feed per revolution using the spindle speed beforehand.
Does the result include return movements?
Only if their distance and speed are identical and included in the input data. Generally, they require a separate calculation.
How are different passes handled?
Calculate each pass with its own length and feed, then add the durations. The pass count on this page represents identical repetitions only. An unweighted average of feeds may produce an incorrect total time even when total distance is correct.
Why can measured time be longer?
The machine must accelerate, decelerate and sometimes reduce feed because of axis or program limits. Auxiliary times also add to theoretical travel time. Compare matching scopes: cutting time alone, the complete motion, or a cycle including handling and inspection.